Open RFIs

1

From issue & RFI logs

Open RFQs

15

From RFQ trackers

Payment Requests Pending

$24K

7 requests

Invoices To Be Sent

$522K

16 invoices

Payments Paid This Week

$0

0 payments

Weekly Meetings

0

This week

Project Status Overview

Project% CompleteCurrent MilestoneNext MilestoneSchedule Status
Tracy
3%
Mobilization & full demolitionSite clearing, excavation & foundation prep(Aug 7, 2026)Delayed
Pradeep V
34%
FRAMING & STRUCTURALINSPECTION: Exterior Shear/Bracing — Code 341(Jul 30)Delayed
Eswar — 3294 Oxford Ln
4%
PRE-START GATES (framing by others ~95% — blocks everything)Confirm STRUCTURAL SPECIAL INSPECTIONS complete — shear-wall nailing ≤4" OC + epoxy anchors (Simpson SET-XP)(verify)Delayed
On Track: progressing as planned At Risk: potential schedule impact Delayed: behind scheduleTap a project for full details

RFI / RFQ Tracker

RFI

Open

1

Due This Week

0

Overdue

0

Waiting On / Pending

1

RFQ

Open

15

Due This Week

0

Overdue

7

Waiting On / Pending

12

Payments & Invoices

Payment Requests

Pending

$24,400

7 requests

Payments Paid

(This Week)

$0

0 payments

Invoices To Be Sent

(Outstanding)

$521,808

16 invoices

Weekly Meetings

No meetings found in your docs, sheets or email this week.

Internal Office Tasks / Notes

Notes

  • Review scope of work with Raymond — needs Ray's review
  • Bathroom Tile — shower floor + bathroom floor — pending client decision
  • Toilet — brand/model (max 1.28 GPF, EPA WaterSense certified) — pending client decision
  • Vanity Faucet — style, finish (max 1.2 GPM at 60 PSI) — pending client decision
  • Shower Trim Kit — must match Builtwell valve brand — pending client decision
  • Fireplace Tile — surround area — pending client decision

Action Items

  • Review scope of work with Raymond — Oxford Lane · Roland (due Jun 22)
  • Send daily report — Daily Operations · Roland (due Jun 21)
  • Review the lumber quote — Oxford Lane · Roland
  • Get Roof quote — Parkland Project · Anahi, Aryaman (due Aug 4)
  • Get stucco quotes — Parkland Project · Anahi, Aryaman (due Jul 30)
  • Invoice - Reminder: Your payment to H+ Design Build is due — H+ Design Build
  • H+ Design Build - invoice 1177 — H+ Design Build
  • H+ Design Build - invoice [Invoice No.1177] — H+ Design Build

Urgent Action Items

  • Oxford Lane — Review scope of work with RaymondOverdue — Jun 22
  • Daily Operations — Send daily reportOverdue — Jun 21
  • Tracy — schedule slipping on "Mobilization & full demolition"Target Jul 17, 2026
  • Pradeep V — schedule slipping on "INSPECTION: Exterior Shear/Bracing — Code 341"Target Jul 30
  • Pradeep V — CONTACT SPECIAL INSPECTOR Moe Tavakolian — Advanced Testing & Inspection Agency. (Sammy Laboy)Due 5/14/26
  • Pradeep V — CALL 811 — Mark all utilities before excavation. 2 business days required. (Sammy Laboy)Due 5/13/26
  • Pradeep V — Contact Ken Horn (Field Coordinator) — introduce project, confirm inspection sch (Sammy Laboy)Due 5/13/26
  • Pradeep V — Solar company — schedule panel removal before roofing crew begins. Coordinate ti (Builtwell)Due 5/16/26